Sample project · read-only
Customer Portal Relaunch
amberNorthwind Retail Group · Priya Shah · 2026-09-01 to 2027-01-30 · Budget £180,000
Latest status report
Week 8 status — UAT at risk from vendor delay · 2026-10-26
Executive summary
Status moves to amber. The vendor missed the API sandbox handover, delaying UAT by roughly one week. Design sign-off is complete and the checkout flow passed testing, so recovery is possible within the phase if the vendor confirms a plan this week.
Accomplishments
- Design sign-off completed for the returns self-service journey
- Core checkout flow passed regression testing
- Migration communications drafted and awaiting sponsor approval
Next steps
- Sarah Ahmed to chase the vendor and confirm a recovery plan by 28 October
- James Wilson to revise the milestone plan and book UAT by 30 October
- Stand up mock API tests so UAT preparation is not blocked
Issues
- Vendor sandbox handover slipped by one week, delaying UAT start
Decisions
- Keep the current launch scope and review the revised schedule at next week's sync
Intake
- Objectives
- Replace the ageing customer portal with a self-service platform: single sign-on, order tracking, returns self-service and a support hub, cutting inbound support contacts by 30%.
- Scope
- Phase 1 covers account migration, order tracking and returns. Phase 2 adds the support hub and saved-payment checkout. Excludes the mobile app rebuild and warehouse integrations.
- Stakeholders
- Northwind: Helen Marsh (sponsor), IT security, contact-centre leads. Delivery Pilot AI: Priya Shah (PM), Kestrel Systems (vendor), QA contractors.
Want this for your project?
Paste your own meeting notes and get the same report, risks, RAID log and actions in minutes. Free, up to 20 reports a day.
Risk register
| Score | Risk | Owner | Status |
|---|---|---|---|
| 16 high | Further vendor delay pushes the launch date | Priya Shah | mitigating |
| 9 medium | Account migration loses legacy password resets | James Wilson | open |
| 8 medium | Security sign-off for saved-payment checkout slips | Priya Shah | open |
| 4 low | Contact-centre staffing over migration weekend | Helen Marsh | open |
RAID log
| Type | Item | Severity |
|---|---|---|
| assumption | Legacy accounts can be migrated in a single weekend wave | medium |
| issue | Vendor sandbox handover missed | high |
| dependency | UAT blocked on vendor sandbox and test credentials | high |
| dependency | Sponsor approval required before migration comms go out | medium |
| assumption | Contact-centre volume stays within modelled peaks | low |
| issue | Saved-payment checkout needs PCI scheduling | medium |
Action log
| Action | Owner | Due | Priority |
|---|---|---|---|
| Chase Kestrel Systems for the sandbox handover and a written recovery plan | Sarah Ahmed | 2026-10-28 | high |
| Revise the milestone plan and book the UAT sessions | James Wilson | 2026-10-30 | high |
| Prepare mock API tests so UAT preparation can start before sandbox access | Priya Shah | 2026-11-04 | medium |
| Circulate the migration communications pack for sponsor approval | Sarah Ahmed | 2026-11-06 | medium |
| Schedule the PCI review for Phase 2 saved-payment checkout | Priya Shah | — | low |