Northwind Retail Group · Priya Shah · 2026-09-01 to 2027-01-30 · Budget £180,000

Latest status report

Week 8 status — UAT at risk from vendor delay · 2026-10-26

Executive summary

Status moves to amber. The vendor missed the API sandbox handover, delaying UAT by roughly one week. Design sign-off is complete and the checkout flow passed testing, so recovery is possible within the phase if the vendor confirms a plan this week.

Accomplishments

  • Design sign-off completed for the returns self-service journey
  • Core checkout flow passed regression testing
  • Migration communications drafted and awaiting sponsor approval

Next steps

  • Sarah Ahmed to chase the vendor and confirm a recovery plan by 28 October
  • James Wilson to revise the milestone plan and book UAT by 30 October
  • Stand up mock API tests so UAT preparation is not blocked

Issues

  • Vendor sandbox handover slipped by one week, delaying UAT start

Decisions

  • Keep the current launch scope and review the revised schedule at next week's sync

Intake

Objectives
Replace the ageing customer portal with a self-service platform: single sign-on, order tracking, returns self-service and a support hub, cutting inbound support contacts by 30%.
Scope
Phase 1 covers account migration, order tracking and returns. Phase 2 adds the support hub and saved-payment checkout. Excludes the mobile app rebuild and warehouse integrations.
Stakeholders
Northwind: Helen Marsh (sponsor), IT security, contact-centre leads. Delivery Pilot AI: Priya Shah (PM), Kestrel Systems (vendor), QA contractors.

Want this for your project?

Paste your own meeting notes and get the same report, risks, RAID log and actions in minutes. Free, up to 20 reports a day.

Risk register

ScoreRiskOwnerStatus
16 highFurther vendor delay pushes the launch datePriya Shahmitigating
9 mediumAccount migration loses legacy password resetsJames Wilsonopen
8 mediumSecurity sign-off for saved-payment checkout slipsPriya Shahopen
4 lowContact-centre staffing over migration weekendHelen Marshopen

RAID log

TypeItemSeverity
assumptionLegacy accounts can be migrated in a single weekend wavemedium
issueVendor sandbox handover missedhigh
dependencyUAT blocked on vendor sandbox and test credentialshigh
dependencySponsor approval required before migration comms go outmedium
assumptionContact-centre volume stays within modelled peakslow
issueSaved-payment checkout needs PCI schedulingmedium

Action log

ActionOwnerDuePriority
Chase Kestrel Systems for the sandbox handover and a written recovery planSarah Ahmed2026-10-28high
Revise the milestone plan and book the UAT sessionsJames Wilson2026-10-30high
Prepare mock API tests so UAT preparation can start before sandbox accessPriya Shah2026-11-04medium
Circulate the migration communications pack for sponsor approvalSarah Ahmed2026-11-06medium
Schedule the PCI review for Phase 2 saved-payment checkoutPriya Shah—low